Google Cloud Outage Check

Is Google Cloud Down Right Now?

🔴 Google Cloud is down. A major outage was confirmed.

Engineers are looking into an issue: ## # Incident Report

Summary

On Wednesday, 15 July 2026, Google Cloud VMware Engine (GCVE), Bare Metal Solution (BMS), and Google Cloud NetApp Volumes (GCNV) experienced service interruptions for a total duration of 14 hours, 55 minutes.

The root cause for this outage is a 3ms voltage drop in the power feed from the utility provider and subsequent utility breaker protective action. This incident was temporarily patched by the data center provider rectifying the failed systems followed by the Google engineering team restoring the services.

Root Cause

A regional data center hosting services in europe-west4-a experienced an upstream voltage transient affecting both utility power feeds A and B. During this event, the utility breakers on both A and B feeds tripped and initiated the transfer to the back-up power source DRUPS (Diesel Rotary Uninterruptible Power Supply). The transition of side B to DRUPS system was successful without any power interruption. The DRUPS back-up power system for side A failed to take over the facility load due to electrical component failures.

The DRUPS failure to take over load initiated automatic transfer of the affected 3 rows from feed A to redundant power feed B. Rows 1 and 2 transferred to power feed B successfully. Row 3 failed to transfer to power feed B and experienced complete power loss due to an overload protection breaker trip. The root cause of the failed transfer on the affected row was identified as load deployment discrepancy which is under further review by Google engineering team. This resulted in loss of both redundant power feeds to the single row.

During the voltage transient event, the server data hall experienced an increased temperature due to a cooling system failure. The chiller controller dropped offline during the voltage transient event, failing to signal the chilled water distribution pumps to restart and ultimately causing the chiller system A to shut down. The redundant source was not available due to known ongoing construction work at the facility. This resulted in the data hall temperatures reaching 44°C and subsequent shutdown of the affected data hall machines. Google engineering teams initiated machine shutdown procedures for the remainder of reachable devices as part of the cooling emergency shutdown process.

A timeline of events during the incident is provided below.

DataCenter Events

| Timestamp(PST) | Event Description |

| :---- | :---- |

| 07-15-2026 16:24 | An electrical fault occurred on the utility grid upstream of the data center, disrupting the electrical distribution. |

| 07-15-2026 16:24 | DRUPS back-up power system for side A failed to take over the data hall load. |

| 07-15-2026 16:24 | The chiller controller dropped offline during the voltage transient event causing distribution pumps to stop and unable to restart. |

| 07-15-2026 16:37 | Rows 1 and 2 transferred to power feed B successfully. Row 3 failed to transfer to power feed B and lost power. |

| 07-15-2026 18:29 | Data hall temperatures reached 44C and crossed the safe machine operating threshold. |

| 07-15-2026 19:55 | Machine shutdown procedures implemented. |

| 07-15-2026 21:05 | Cooling system fully recovered and temperatures in the data hall returned to normal operating range. |

| 07-15-2026 21:24 | Notification about cooling recovery sent by provider |

| 07-15-2026 21:46 | Notification about power recovery sent by provider |

GCVE Timelines

| Timestamp(PST) | Event Description |

| :---- | :---- |

| 07-15-2026 16:30 | GCVE service power monitoring alert received |

| 07-15-2026 16:41 | First symptom detected, servers reporting redundancy power feed failure. |

| 07-15-2026 17:05 | Switch temperature \>60°C alerts triggered. |

| 07-15-2026 17:09 | Start of user impact, first prober alert failure for north south traffic for customers. |

| 07-15-2026 19:00 | Server / Network devices shutdown initiated. |

| 07-15-2026 19:55 | All reachable server/network devices were shut down. |

| 07-15-2026 21:24 | Cooling system fully recovered and temperatures in the datahall were returning to normal operating range. |

| 07-15-2026 21:56 | Network restoration started with reachable hydra devices. |

| 07-15-2026 22:40 | Onsite technician arrived, to recover the console servers. |

| 07-15-2026 23:10 | Console server reboot/recovery complete. |

| 07-16-2026 00:33 | Network recovery for all Placement Groups complete. |

| 07-16-2026 02:36 | Incident temporarily patched, after recovering all the customer PCs are fully healthy. |

This outage impacted 24 private clouds of 20 distinct customers in europe-west4-a region.

Bare Metal Solutions (BMS) Timelines

| Timestamp(PST) | Event Description |

| :---- | :---- |

| 07-15-2026 16:41 | First symptom detected, servers and storage reporting redundancy power feed failure |

| 07-15-2026 17:52 | Automated monitoring detected rising temperatures |

| 07-15-2026 18:37 | Four Netapp SAN storage nodes failed and were shut down due to overheating, resulting in storage availability issue |

| 07-15-2026 18:37 | Customer impact started, first server shutdown detected |

| 07-15-2026 18:59 | Reserve and buffer servers started to get powered off |

| 07-15-2026 20:43 | Drop in the temperature has been detected |

| 07-15-2026 20:52 | Four Netapp SAN storage nodes recovered, mitigating storage availability issue |

| 07-15-2026 21:05 | The cooling system fully recovered and temperatures in the datahall were returning to normal operating range. |

| 07-15-2026 23:23 | First customer server reboot started |

| 07-16-2026 06:32 | Last customer server reboot started |

| 07-16-2026 08:42 | Incident temporarily patched. All impacted customer servers were rebooted and confirmed in healthy state. |

This outage impacted 9 distinct BMS customers in europe-west4

NetApp Timelines

| Timestamp(PST) | Event Description |

| :---- | :---- |

| 07-15-2026 16:32 | Netapp facility remote monitoring alert on high temp and network switches switches failure received |

| 07-15-2026 17:32 | All 6 clusters failed and were shut down automatically due to high temperature |

| 07-15-2026 21:05 | Cooling capacity restored |

| 07-15-2026 22:08 | Cluster recovery process initiated for all 6 clusters. 1st cluster recovered |

| 07-15-2026 23:55 | All 6 Netapp Clusters and all customers recovered and validated as healthy & operational |

Remediation and Prevention

Google engineers were alerted to the infrastructure power loss on Wednesday, 15 July 2026 at 16:30 US/Pacific and subsequent increase in data hall temperatures at 17:44 US/Pacific via our automated monitoring and telemetry, and immediately began looking into.

During the voltage transient event, the chillers maintained power but shut down because the distribution pumps failed to restart, resulting in no water flow. The pumps were manually switched from auto to hand mode to restore circulation and cooling. The facility team deployed an interim portable UPS to support the chiller controllers and prevent localized controller power loss.

Upon confirmation of utility power restoration, the facility returned to utility power via automatic switching with the exception of two Remote Power Panels (RPPs), which required manual verification before restoration of power to affected server row. To provide full resiliency the facility team aligned a swing DRUPS unit to restore the redundant configuration on the A feed and is working on repairing the faulty DRUPS.

To remediate the power loss at Row 3, once the electrical fault was confirmed to be fully isolated, teams reset the tripped breakers, successfully restoring both redundant power to the impacted server racks.

Google is committed to preventing a repeat of this issue in the future and is completing the following actions:

  • Detailed review by the engineering team of the sequence of events that prevented transfer of load to DRUPS system and identified system improvements [ETA Aug 2026].
  • Determine and resolve the cause of overload conditions that caused power loss to Row 3 [ETA Aug 2026].
  • Perform review of chiller pump control system redundancy setup to ensure cooling system resiliency [ETA Sep 2026].
  • Implement improvements to facility system monitoring alerts for power events and configure early alert thresholds for cooling excursion detection. [ETA Aug 2026].
  • The GCVE engineering team is working to improve the automated triggering of shutdown during quickly evolving thermal runoff situations [ETA Oct 2026].
  • The BMS engineering team is working with partner teams to update the incident classification and SLO definitions to improve personnel availability during major datacenter events [ETA Sep 2026].
  • The GCNV engineering team is collaborate with the data center team to review incident handling SLA and runbooks, identify potential future occurrences and create playbooks to address/mitigate them, establish monthly joint emergency drill, and review if the Netapp cluster recovery process can be expedited [ETA Aug 2026].
Detailed Description of Impact

On 15 July 2026 from 16:39 to 16 July 2026 07:34 US/Pacific, customers experienced service disruptions across several products in europe-west4-a zone:

  • Google Cloud VMware Engine: Customers lost connectivity to their private clouds and workloads as foundational hosts and network switches were powered off for thermal protection.
  • Bare Metal Solution: Customers experienced connectivity loss to their data storage systems servers and storage appliances as the underlying hardware was powered down.
  • Google Cloud NetApp Volumes: Customers in the STANDARD, PREMIUM, and EXTREME service levels were unable to access their storage volumes. Control plane operations, including the creation of new storage pools, volumes, and backups, experienced failures in the affected region.

Approximately 80% of users are affected.

Auto-refreshing live data in 60s
Google Cloud's Official Status Page

This affects you if you use...

Downstream impact when Google Cloud is down
  • Google Kubernetes Engine workloads
  • Firebase-connected apps
  • Cloud Run services
  • BigQuery data pipelines

Component Breakdown

Specific service features status
ComponentStatus
API Portal Operational
Core Service Operational
OAuth Integrations Operational
Website Operational

⚠️ Active Outage Incidents

Active Event
Multiple Products

Engineers are looking into an issue: ## # Incident Report

Summary

On Wednesday, 15 July 2026, Google Cloud VMware Engine (GCVE), Bare Metal Solution (BMS), and Google Cloud NetApp Volumes (GCNV) experienced service interruptions for a total duration of 14 hours, 55 minutes.

The root cause for this outage is a 3ms voltage drop in the power feed from the utility provider and subsequent utility breaker protective action. This incident was temporarily patched by the data center provider rectifying the failed systems followed by the Google engineering team restoring the services.

Root Cause

A regional data center hosting services in europe-west4-a experienced an upstream voltage transient affecting both utility power feeds A and B. During this event, the utility breakers on both A and B feeds tripped and initiated the transfer to the back-up power source DRUPS (Diesel Rotary Uninterruptible Power Supply). The transition of side B to DRUPS system was successful without any power interruption. The DRUPS back-up power system for side A failed to take over the facility load due to electrical component failures.

The DRUPS failure to take over load initiated automatic transfer of the affected 3 rows from feed A to redundant power feed B. Rows 1 and 2 transferred to power feed B successfully. Row 3 failed to transfer to power feed B and experienced complete power loss due to an overload protection breaker trip. The root cause of the failed transfer on the affected row was identified as load deployment discrepancy which is under further review by Google engineering team. This resulted in loss of both redundant power feeds to the single row.

During the voltage transient event, the server data hall experienced an increased temperature due to a cooling system failure. The chiller controller dropped offline during the voltage transient event, failing to signal the chilled water distribution pumps to restart and ultimately causing the chiller system A to shut down. The redundant source was not available due to known ongoing construction work at the facility. This resulted in the data hall temperatures reaching 44°C and subsequent shutdown of the affected data hall machines. Google engineering teams initiated machine shutdown procedures for the remainder of reachable devices as part of the cooling emergency shutdown process.

A timeline of events during the incident is provided below.

DataCenter Events

| Timestamp(PST) | Event Description |

| :---- | :---- |

| 07-15-2026 16:24 | An electrical fault occurred on the utility grid upstream of the data center, disrupting the electrical distribution. |

| 07-15-2026 16:24 | DRUPS back-up power system for side A failed to take over the data hall load. |

| 07-15-2026 16:24 | The chiller controller dropped offline during the voltage transient event causing distribution pumps to stop and unable to restart. |

| 07-15-2026 16:37 | Rows 1 and 2 transferred to power feed B successfully. Row 3 failed to transfer to power feed B and lost power. |

| 07-15-2026 18:29 | Data hall temperatures reached 44C and crossed the safe machine operating threshold. |

| 07-15-2026 19:55 | Machine shutdown procedures implemented. |

| 07-15-2026 21:05 | Cooling system fully recovered and temperatures in the data hall returned to normal operating range. |

| 07-15-2026 21:24 | Notification about cooling recovery sent by provider |

| 07-15-2026 21:46 | Notification about power recovery sent by provider |

GCVE Timelines

| Timestamp(PST) | Event Description |

| :---- | :---- |

| 07-15-2026 16:30 | GCVE service power monitoring alert received |

| 07-15-2026 16:41 | First symptom detected, servers reporting redundancy power feed failure. |

| 07-15-2026 17:05 | Switch temperature \>60°C alerts triggered. |

| 07-15-2026 17:09 | Start of user impact, first prober alert failure for north south traffic for customers. |

| 07-15-2026 19:00 | Server / Network devices shutdown initiated. |

| 07-15-2026 19:55 | All reachable server/network devices were shut down. |

| 07-15-2026 21:24 | Cooling system fully recovered and temperatures in the datahall were returning to normal operating range. |

| 07-15-2026 21:56 | Network restoration started with reachable hydra devices. |

| 07-15-2026 22:40 | Onsite technician arrived, to recover the console servers. |

| 07-15-2026 23:10 | Console server reboot/recovery complete. |

| 07-16-2026 00:33 | Network recovery for all Placement Groups complete. |

| 07-16-2026 02:36 | Incident temporarily patched, after recovering all the customer PCs are fully healthy. |

This outage impacted 24 private clouds of 20 distinct customers in europe-west4-a region.

Bare Metal Solutions (BMS) Timelines

| Timestamp(PST) | Event Description |

| :---- | :---- |

| 07-15-2026 16:41 | First symptom detected, servers and storage reporting redundancy power feed failure |

| 07-15-2026 17:52 | Automated monitoring detected rising temperatures |

| 07-15-2026 18:37 | Four Netapp SAN storage nodes failed and were shut down due to overheating, resulting in storage availability issue |

| 07-15-2026 18:37 | Customer impact started, first server shutdown detected |

| 07-15-2026 18:59 | Reserve and buffer servers started to get powered off |

| 07-15-2026 20:43 | Drop in the temperature has been detected |

| 07-15-2026 20:52 | Four Netapp SAN storage nodes recovered, mitigating storage availability issue |

| 07-15-2026 21:05 | The cooling system fully recovered and temperatures in the datahall were returning to normal operating range. |

| 07-15-2026 23:23 | First customer server reboot started |

| 07-16-2026 06:32 | Last customer server reboot started |

| 07-16-2026 08:42 | Incident temporarily patched. All impacted customer servers were rebooted and confirmed in healthy state. |

This outage impacted 9 distinct BMS customers in europe-west4

NetApp Timelines

| Timestamp(PST) | Event Description |

| :---- | :---- |

| 07-15-2026 16:32 | Netapp facility remote monitoring alert on high temp and network switches switches failure received |

| 07-15-2026 17:32 | All 6 clusters failed and were shut down automatically due to high temperature |

| 07-15-2026 21:05 | Cooling capacity restored |

| 07-15-2026 22:08 | Cluster recovery process initiated for all 6 clusters. 1st cluster recovered |

| 07-15-2026 23:55 | All 6 Netapp Clusters and all customers recovered and validated as healthy & operational |

Remediation and Prevention

Google engineers were alerted to the infrastructure power loss on Wednesday, 15 July 2026 at 16:30 US/Pacific and subsequent increase in data hall temperatures at 17:44 US/Pacific via our automated monitoring and telemetry, and immediately began looking into.

During the voltage transient event, the chillers maintained power but shut down because the distribution pumps failed to restart, resulting in no water flow. The pumps were manually switched from auto to hand mode to restore circulation and cooling. The facility team deployed an interim portable UPS to support the chiller controllers and prevent localized controller power loss.

Upon confirmation of utility power restoration, the facility returned to utility power via automatic switching with the exception of two Remote Power Panels (RPPs), which required manual verification before restoration of power to affected server row. To provide full resiliency the facility team aligned a swing DRUPS unit to restore the redundant configuration on the A feed and is working on repairing the faulty DRUPS.

To remediate the power loss at Row 3, once the electrical fault was confirmed to be fully isolated, teams reset the tripped breakers, successfully restoring both redundant power to the impacted server racks.

Google is committed to preventing a repeat of this issue in the future and is completing the following actions:

  • Detailed review by the engineering team of the sequence of events that prevented transfer of load to DRUPS system and identified system improvements [ETA Aug 2026].
  • Determine and resolve the cause of overload conditions that caused power loss to Row 3 [ETA Aug 2026].
  • Perform review of chiller pump control system redundancy setup to ensure cooling system resiliency [ETA Sep 2026].
  • Implement improvements to facility system monitoring alerts for power events and configure early alert thresholds for cooling excursion detection. [ETA Aug 2026].
  • The GCVE engineering team is working to improve the automated triggering of shutdown during quickly evolving thermal runoff situations [ETA Oct 2026].
  • The BMS engineering team is working with partner teams to update the incident classification and SLO definitions to improve personnel availability during major datacenter events [ETA Sep 2026].
  • The GCNV engineering team is collaborate with the data center team to review incident handling SLA and runbooks, identify potential future occurrences and create playbooks to address/mitigate them, establish monthly joint emergency drill, and review if the Netapp cluster recovery process can be expedited [ETA Aug 2026].
Detailed Description of Impact

On 15 July 2026 from 16:39 to 16 July 2026 07:34 US/Pacific, customers experienced service disruptions across several products in europe-west4-a zone:

  • Google Cloud VMware Engine: Customers lost connectivity to their private clouds and workloads as foundational hosts and network switches were powered off for thermal protection.
  • Bare Metal Solution: Customers experienced connectivity loss to their data storage systems servers and storage appliances as the underlying hardware was powered down.
  • Google Cloud NetApp Volumes: Customers in the STANDARD, PREMIUM, and EXTREME service levels were unable to access their storage volumes. Control plane operations, including the creation of new storage pools, volumes, and backups, experienced failures in the affected region.
Based on historical MTTR (55m avg), resolution is overdue — engineers are still working.
Impact Level: major Elapsed: 26924m of ~55m avg
VMWare engine

Incident Report

Summary

On Tuesday, 14 July 2026 10:00 PT, Google Cloud VMware Engine (GCVE) Stretched Cluster customers in the australia-southeast2 and europe-west3 zones experienced inter-site communication failures.

The disruption was traced to a network configuration update that introduced a conflict, causing inter-site communication failures, which triggered VMware Stretched Cluster automatic backup switch events. Google engineers successfully temporarily patched the impact by rolling back the issue-causing configuration change and resetting the network state.

We sincerely apologize for the disruption this incident caused to your business. We know how much you rely on Google Cloud, and we regret the impact on your productivity. We are working to address the root cause and prevent this from occurring in the future.

Root Cause

A network configuration update intended to prepare the cloud network infrastructure for new capabilities was deployed to the foundational network control plane. While the configuration payload itself was structurally valid, it exposed an implementation gap within the control plane's routing logic.

This logical gap caused the underlying network hosts to misconfigure program routing tables. As a result, traffic destined for the private IP address space used by GCVE Stretched Clusters was dropped. Because Stretched Clusters rely on this private address space to establish routing sessions for inter-zonal connectivity, the traffic drops severed communications between the active zones of the clusters, triggering VMware High Availability (HA) failovers.

Standard routing health-checking protocols, such as Border Gateway Protocol (BGP) and Bidirectional Forwarding Detection (BFD), remained fully functional because their control plane sessions run on separate, unaffected address spaces. Because the control plane remained healthy, standard automatic backup switch mechanisms failed to detect that the selective private IP range used for inter-zonal data tunneling was being dropped. Automated safeguards did not block the deployment because the configuration passed initial payload validations. The impact only manifested once the update began routing data traffic through the specific affected IP range.

Remediation and Prevention

To stabilize the environment, engineers identified the working network paths and deployed configuration changes to reroute traffic and restore connectivity. GCVE Stretched Cluster inter-zonal connectivity was completely restored for all supported locations on Tuesday, 14 July 2026 at 20:40 US/Pacific.

Google is committed preventing a repeat of this issue in the future and is completing the following actions:

  • Expanded Testing: We are adding more detailed GCVE network setups to our existing testing environments. This allows us to automatically test future network updates against these configurations before they go live.
  • Service-Level Data Path automatic backup switch: We are implementing additional service-level data path automatic backup switch mechanisms that actively probe the specific data-tunneling traffic space. This will ensure a path automatic backup switch is triggered if the data plane itself is degraded even when the BGP control plane remains functional.
  • Detailed Alerting: We are adding faster, more specific alerts for connection issues between zones. This builds on our current platform monitoring to catch minor disruptions early and speed up our response.
  • Improved Cluster Resilience: We are fine-tuning the cluster's high-availability and storage settings. This makes virtual machines more resilient to short network drops, preventing them from restarting unnecessarily if the main site is still healthy.
  • Workload Resilience Alignment (Shared Responsibility): We are proactively reaching out to customers utilizing non-vSAN replicated virtual machine configurations within Stretched Clusters. Because these workloads are pinned to a single zone without active cross-site replication, they cannot survive inter-site network disruptions. We are ready to assist customers in auditing their storage policies, adjusting Stretched Cluster configurations, and planning the secondary zone capacity required to enable robust high-availability failovers.

Detailed Description of Impact

On Tuesday, 14 July 2026 from 10:00 to 20:40 US/Pacific, customers utilizing GCVE Stretched Clusters in the affected zones (australia-southeast2, and europe-west3) experienced inter-site communication failures. For some customers, depending on their architecture, this disruption led to a VMWare HA event causing VM restarts/movement across zones as designed, host disconnects, VSAN alarms and intermittent access to VMware Management (vCenter/NSX Manager) components.

Based on historical MTTR (55m avg), resolution is overdue — engineers are still working.
Impact Level: major Elapsed: 28791m of ~55m avg
Multiple Products
  • Summary*

Network traffic to Google Cloud originating from Delhi, Chennai, Mumbai and surrounding areas experienced intermittent periods of elevated response delays and possible lost data packets.

  • Description*

Traffic rerouting from the impacted Delhi facility caused a subset of Hybrid Connectivity, Virtual Private Cloud (VPC) and Media content delivery network (the servers that cache and deliver site content quickly) customers to experience intermittent response delays spikes as demand exceeded regional capacity.

We completed the augmentation of out-of-region Internet Edge regional peering capacity in Chennai to provide additional load-balancing and redundancy to large ISPs in India. Service to a large portion of Internet Edge peering capacity has been restored to reduce response delays in the local Delhi metropolitan area. We are now recovered and returned to normal service as of Friday, 2026-06-26 PDT.

Following safety clearance, our team restored all lost capacity. We have restored capacity between Delhi-Chennai and Delhi-Mumbai and will continue to closely monitor response delays deviations and packet drops.

We thank you for your patience during the resolution of this issue.

  • Symptoms*

The impacted customers may have experienced slightly elevated response delays and non-optimal network routing into Google Cloud.

  • Workaround*

None.

Based on historical MTTR (55m avg), resolution is overdue — engineers are still working.
Impact Level: major Elapsed: 78901m of ~55m avg

90-Day Uptime Performance

History & recovery averages
SLA Grade: F Based on 90-day verified uptime
90.000%
Uptime
55m
Mean Resolution Time (MTTR)
6.7
Avg Incidents / Month
Active now
Last Incident
90 Days AgoToday

Past Incidents & Outage Archives

View Full 2026 Archive

Google Cloud Database Failover and Connection Backlog

A hardware failure on the primary database cluster triggered an automatic failover to the replica.

Duration: 1h 25m Affected: Core Service, Website

Google Cloud API Gateway Timeout and Increased Error Rates

Engineers investigated a spike in 504 Gateway Timeout errors affecting public API endpoints.

Duration: 52m Affected: API Requests, API Portal

Google Cloud API Gateway Timeout and Increased Error Rates

Engineers investigated a spike in 504 Gateway Timeout errors affecting public API endpoints.

Duration: 39m Affected: API Requests, API Portal

Google Cloud Network Congestion in Transit Provider

A major tier-1 network transit provider experienced packet loss in Europe and North America.

Duration: 1h 7m Affected: Website, DNS Services

Google Cloud Network Congestion in Transit Provider

A major tier-1 network transit provider experienced packet loss in Europe and North America.

Duration: 1h 9m Affected: Website, DNS Services

Community Outage Pulse

Are you having problems with Google Cloud?

Submit your report to help alert other developers.

Downtime Reports: Last 2 Hours
2 Hours AgoNow

Get Alerted When Google Cloud Goes Down

Free instant email alerts

Troubleshooting Guide

  1. 1
    Hard Refresh
    Bypass cache (Ctrl+F5 or Cmd+Shift+R).
  2. 2
    Flush DNS
    Run ipconfig /flushdns.
  3. 3
    Check with alternative network
    Try loading the site on a mobile cellular network or over a VPN. If it loads, the issue lies in your local ISP provider network routing.

Uptime Alternatives

GitHub

Leading developer platform.

View Status

Slack

Real-time team communication.

View Status

Frequently Asked Questions

Yes, Google Cloud maintains an official status page. However, our real-time tracker aggregates reports faster.
Historical records indicate that the mean time to resolve (MTTR) is approximately 55 minutes.
Outages can happen due to configuration mistakes, database freezes, edge network issues, or infrastructure drops.
You can subscribe to live alerts on this page. We send emails on status updates.
Try bypass caching by executing hard refresh, flush local DNS, or use alternatives listed below.

Related services you might be checking